The Nusantara Capital Authority (IKN) has made significant progress in developing the core infrastructure of the new capital city, with the main road construction reaching 99% completion. The project includes seven contract packages (A-G) that will connect key areas such as government facilities, educational institutions, and residential areas. This infrastructure development is crucial for supporting the future government's activities and the overall functionality of the new capital city.

Full Analysis
02

Deep Dive Analysis

IKN Infrastructure Development: Main Road Construction Nears Completion

Comprehensive Infrastructure Project

The Nusantara Capital Authority (IKN) continues to advance the development of basic infrastructure as the backbone of connectivity in the Core Government Area (KIPP) of the new capital city. The current focus is on the construction of Road 1B - 1C, designed as the main road in KIPP IKN, playing a crucial role in connecting various strategic plots, including educational areas, government facilities, and residential zones.

Progress Update on Road Construction

According to the IKN Authority's report on January 7, 2026, the road network development is being executed through seven contract packages (A-G), with an average construction progress reaching 99%. These roads will not only support daily mobility but also serve as connectors between different functional areas that will support government activities and community life in IKN.

Detailed Progress by Contract Package:

  1. Package A: 99% progress, covering Section 1 (1.3 km) connecting vertical ASN housing to PSSI Field.
  2. Package B: 100% progress, covering Section 2 (1.9 km) passing through strategic plots including Al-Azhar School.
  3. Package C: 100% progress, covering Section 3 (1.8 km) serving access to educational areas like Taruna Nusantara School.
  4. Package D: 100% progress, covering Section 5 (2.2 km) supporting connectivity between investment plots in the warehouse hub area.
  5. Package E: 99% progress, covering PSSI ring road (2.2 km) connecting PSSI Field and Mayapada Hospital.
  6. Package F: 100% progress, covering a 2.5 km road connecting to Tol Seksi 6C, passing through plots towards Abdi Waluyo Hospital.
  7. Package G: 100% progress, covering Section 4 (1 km) leading to Taruna Nusantara School.

Significance of Infrastructure Development

The construction of Road 1B and 1C is a vital component in creating an integrated, safe, and efficient transportation system in KIPP IKN. The presence of this main road network is expected to support the smooth operation of government activities, educational services, healthcare facilities, and residential areas for state apparatus and the community in IKN.

The IKN Authority remains committed to ensuring that infrastructure development meets quality and timeline standards, providing optimal benefits for the realization of Nusantara as Indonesia's future capital city.

Original Sources
03

Source References

Click any source to view the original article in a new tab

Story Info

Published
1 week ago
Read Time
13 min
Sources
1 verified

Topics Covered

Infrastruktur IKNPembangunan JalanProgres Konstruksi

Key Events

1

IKN Infrastructure Development Progress

2

Main Road Construction Update

Timeline from 1 verified sources