PLN Accelerates Recovery of Damaged 150 kV Transmission Line in Jakarta

AnalisaHub Editorial·December 5, 2025
Executive Summary
01

Executive Summary

Key insights and market outlook

PT PLN (Persero) has accelerated the recovery and security measures for its 150 kV transmission line in Palmerah, Jakarta, following a disruption caused by a broken Ground Steel Wire (GSW) 1

2. The incident occurred between the Karet Lama and Angke transmission lines. No casualties were reported despite the disruption, thanks to swift action by PLN and collaboration with local authorities 2.

Full Analysis
02

Deep Dive Analysis

PLN Swiftly Responds to Jakarta Transmission Line Disruption

Incident Overview

PT PLN (Persero) Unit Induk Transmisi Jawa Bagian Barat (UIT JBB) quickly responded to a disruption in the 150 kV transmission line between Karet Lama and Angke in Palmerah, Jakarta Barat 1

2. The incident was caused by the breaking of a Ground Steel Wire (GSW) on the transmission line.

Recovery Efforts

PLN's response included deploying numerous personnel to secure the installation and ensure the surrounding area was safe 2

. The company worked in collaboration with various local agencies, including the Jakarta Barat Regional Disaster Management Agency (BPBD), fire department, local government, and Palmerah police sector. Their efforts focused on maintaining public safety and supporting evacuation processes, including providing tents and basic necessities for affected communities.

Safety and Operational Measures

Manager Komunikasi & TJSL PLN UIT JBB, Gita Kurniawan Ginting, stated that a comprehensive inspection was conducted to ensure the reliability of transmission installations around the affected area 1

. The inspection included checking tower structures, conductor wires, and supporting equipment that could have been impacted. Additionally, the network was secured as part of mitigation efforts to ensure the area remained safe for the public and operational stability was maintained.

Impact and Outcomes

The swift action by PLN and collaborating agencies ensured that there were no casualties resulting from the incident 2

. The electricity system in Jakarta was confirmed to be safe, maintaining stability in the region's power supply.

Original Sources

Story Info

Published
1 month ago
Read Time
11 min
Sources
2 verified

Topics Covered

Energy InfrastructureTransmission Line DisruptionPLN Operations

Key Events

1

Transmission Line Disruption

2

PLN Recovery Efforts

Timeline from 2 verified sources