Key insights and market outlook
PTPP has achieved 93.94% progress in the construction of the Probolinggo-Banyuwangi toll road package 3 as of December 2025. The project, valued at Rp 1.99 trillion, is expected to be completed by March 2026. The 25.6 km toll road is being developed through a joint operation with PTPP leading the construction with a 50% share.
PTPP has made significant progress in the construction of the Probolinggo-Banyuwangi toll road package 3, achieving 93.94% completion as of December 2025. The project is on track to be operational by March 2026.
The toll road spans 25.6 kilometers from STA 20+200 to STA 45+800, located in Probolinggo and Situbondo regencies, East Java. PTPP is leading the construction as part of a joint operation (JO) with a 50% stake. The contract value for PTPP's portion is Rp 1.99 trillion.
This infrastructure project is crucial for enhancing connectivity in East Java, supporting economic development in the region. The Probolinggo-Banyuwangi toll road is expected to improve transportation efficiency and stimulate local economic activities once completed.
Toll Road Construction Progress Update
Infrastructure Project Milestone